Tentative Project Schedule
Notice to Proceed |
5/23/2012 |
Complete |
Draft Baseline Hydrology |
8/2/2012 |
Complete |
Final Baseline Hydrology |
9/11/2012 |
Complete |
Draft Alternatives Evaluation |
10/21/2013 |
Complete |
Final Alternatives Evaluation |
3/21/2014 |
Complete |
Draft Conceptual Preliminary Design Report |
7/15/2014 |
Upcoming |
Final Conceptual Preliminary Design Report |
8/27/2014 |
Upcoming |
Draft FHAD Report |
2/28/14 |
Complete |
Final FHAD Report |
4/25/14 |
Upcoming |
For more information see Project Deliverables for descriptions and available downloads.